Middle East Steel Industry

Steelmaking capacity in the Middle East is growing rapidly. Demand for steel in the region is expanding as higher energy and raw material prices increase income and boost investment in the region. Producers in the region are planning to expand capacity to meet this growth in demand, especially in long products production such as reinforcing steel. Steelmaking capacity in this region is projected to rise from 32.3 million tpy in 2007 to 56 million tpy in 2010.

Iran, the major producer in the region, plans to raise capacity from 13.3 million tpy in 2007 to 31.8 million tpy by 2010. Mobarakeh Steel Company (MSC) is a large player in Iran who will raise capacity at Esfahan from 4.2 to 5.4 million tpy. The project is one of three that will take MSC’s flat products capacity to 9 million tpy by 2010. The project will focus on MSC’s steel melting facilities. Other projects are the 700,000 tpy Saba thin-slab mini-mill and the Shahid Kharazi project, which will provide additional capacity of 2 million tpy.

Esfahan Steel, Iran’s largest long products producer, plans to expand its crude steel capacity from 2.2 million tpy to 3.6 million tpy by 2008. The company became the country’s first producer of H-beams. Alborz Steel is building a new steel plant on the Persian Gulf coast that will gain its own meltshop in the second phase of development.

Gamborn Steel has plans to build a 2 million tpy electric-arc furnace by March 2009. This would make it the largest private crude steelmaker in Iran. Ardebil Steel planned to start up a billet plant in Iran in March 2008. The 500,000 tpy meltshop will be fed with scrap or direct reduction iron. The electric-arc furnaces and transformers, as well as ladle furnace and continuous caster, have already been installed and other machinery is being shipped to Iran.

The state-owned Arfa Iron & Steel Company will build an 800,000 tpy steel plant in the Ardakan Iron & Steel complex. The project will comprise an 800,000 tpy electric-arc furnace and a continuous caster producing slab, fed by a direct reduced iron (DRI) plant.

A ceremony in Baft marked the start of construction of Baft Steel, one of eight direct reduced iron-fed mini-mills NISCO has committed to building by 2010. The company will have billet capacity of 800,000 tpy and is one of the eight steel projects that the Iranian government is promoting in order to stimulate growth in economically undeveloped areas of the country.

Essar Pars Steel Company, a joint venture which is majority owned by the Indian steelmaker Essar, started building a 3 million tpy direct reduced iron plant and a 1.4 million tpy billet making mini-mill in Iran in 2007. The first phase is scheduled for commissioning by 2009.

Iran Alloy Steel Co (Iasco) has signed an engineering, procurement and construction contract with a consortium of Iranian firms in order to more than double its alloy steel capacity to 450,000 tpy. The company has a separate project to build a carbon steel mini-mill with capacity of 650,000 tpy.

Iran National Steel Industrial Group has begun production at its new 430,000 tpy billetmaking facility and aimed to reach full capacity by the end of 2007. The new meltshop produces billet, fed by a 60-tonne electric-arc furnace.

Iran’s Mines & Metals Technological Engineering Company (MMTE) was set to provide a new direct reduced iron plant to the Khouzestan Steel Company (KSC) in May 2008. The Zamzam II DRI plant will have a capacity of 960,000 tpy. It is part of KSC’s development plans to increase its semi-finished steel product capacity to 3.2 million tpy from 2.2 million.

Safa Industrial Group has begun to build the Middle East’s largest steel plant in the Iranian city of Khorramshahr. The plant will have designed capacity of 9.2 million tpy of crude steel. In the first phase Safa will begin producing some hot-rolled coil and plate by the end of 2008, before ramping up to full production by the end of 2010.

India’s Tata Steel has won approval from the Iranian government to set up a 3 million tpy steel project in the country. The project could be commissioned in three years from the start of construction, though it remains unclear when Tata Steel will be able to start work on the project.

The Iranian Mines & Mineral Industries Development & Renovation Organization has allocated USD 450 million for the development of a new steelmaking plant in the Hormozgan province. The works, which is scheduled for commissioning in the summer of 2009 near Bandar Abbas on the Persian Gulf, will initially produce 1.5 million tpy of slab.

In Bahrain, United Stainless Steel Company is in the process of building a 90,000 tpy coldrolling mill in Bahrain. The USD 210 million mill will be the first stainless strip producer in the Gulf region.

In Egypt, Al Ezz Steel Rebars plans to install a new 1.35 million tpy EAF-based meltshop and a 800,000 tpy thin-slab caster at its majority-owned subsidiary Al Ezz Flat Steel (EFS), where output of finished products will also increase by 800,000 tpy.

ArcelorMittal will build a 1.6 million tpy DRI-based steelworks after a placing a bid for USD 62 million. The company intends to start construction of the 1.6 million tpy plant and a 1.4 million tpy billet-making electric-arc furnace steel plant in 2009, which will be located on Egypt’s northern Red Sea coast. The licence was auctioned by Egypt’s Ministry of Trade and Industry and is one of four DRI-based steel expansions the Egyptian government has recently approved.

In Iraq, The government remains open to approaches to reopen the State Company for Iron & Steel in Basra, the steel plant destroyed in the Gulf Wars, despite the failure of a privatisation attempt in the middle of 2007. A 1.1 million tpy direct reduced iron plant, four electric-arc furnaces, two 6-strand continuous casters for 100-150mm square billet, a 12-32mm twist-type bar rolling mill and a UPN sections mill are all still on site. In Kuwait, United Steel Industries Company has plans to increase output to one million tons in 2008.

In Oman, Jindal Saw International, a subsidiary of India’s Jindal Saw, has signed a Memorandum of Understanding with United Arab Emirates-based Shadeed Iron & Steel to set up a one million tpy seamless tube plant in Oman’s Sohar Industrial Port, with commercial production to start by the third quarter of 2008.

In Qatar, Qatar Steel is planning to start a joint venture with India’s Essar Group to build a 4 million tpy integrated steel plant in Qatar’s Mesaieed industrial city. Meanwhile the company has successfully commissioned its new bar mill, with productivity of 700,000 tpy, which will raise its production of rebar to around 1.5 million tpy.

In Saudi Arabia, Al Tuwairqi Group (ATG) plans to add 400,000 tpy of crude steel production at its Jeddah facility by 2009, where there is currently no meltshop production. ATG has commissioned a 1.35 million tpy bar mill to cater to the growing demand for long products in the Gulf region. The mill has been built in Jeddah to produce rebar, round and flat bars in carbon and engineering steels. The company also plans to expand its meltshop capacity at the Damman facility by 600,000 tpy by 2009. Pan Kingdom Invest Company plans to build a USD 250 million mini-mill in Jizan Economic City. In April 2007, the company chose the German plant-making group SMS to supply a 1 million tpy meltshop and a 500,000 tpy rebar rolling mill, which is scheduled for commissioning by mid-2009. Unicoil is planning to build a 3 million tpy flat products mini-mill. Construction of the works is due to start in the first half of 2008 after final project approval. The initial plan is to have a meltshop with a continuous slab caster fed by a captive DRI plant and a hot strip mill.

In the United Arab Emirates, Emirates Steel Industries has awarded the Italian plant-maker Danieli a USD 1 billion contract to build a new mini-mill in Abu Dhabi. It will be located in the Mussaffah Industrial Area and include a 1.6 million tpy direct reduced iron plant and a 1.4 million tpy steel meltshop. It currently produces around 720,000 tpy of rebar. It will have a 620,000 tpy high speed bar mill and a 480,000 tpy wire rod mill. Emirates plans to increase its crude steel capacity to 5 million tpy in 2012. ETA-Ascon Group hopes to install a 800,000 tpy meltshop in Fujeirah. A contract is close to being signed and commissioning would be towards the end of 2008. Construction of the meltshop would take Star Steel’s total investment to around USD 150 million.

In Yemen, Al-Rahabi Trading Industrial Group plans to develop the country’s first integrated iron and steel works at a cost of USD 250 million. The new facility will have a production capacity of 1 million tpy and will be developed in co-operation with Kuwaiti, Saudi, Qatari, and UAE-based investors on a 400,000 square meter site. The new mill will be the largest in Yemen and will be fed by iron ore exploited from Yemeni mines. Saudi Arabia’s Al-Tuwairqi Group plans to invest USD 1 billion in Yemen to build steel and power plants. The steel plant will have a capacity of 5 million tonnes of liquid steel. In addition, the company will build a rolling mill which will produce 1 million tonnes of rebar annually. The investment includes installation of a power plant. The plant will operate by 2011.

Iran: Steel Industry Overview

The establishment of iron and steel plants in Iran has been in the mind of the country’s government since the early decade of the 20th century. The first serious attempt was made in late 1930s with the assistance of German companies. But the outbreak of the World War II brought the construction works to standstill and the project was never completed.
Almost two decades after the World War II due to recovery in economic situation and increasing demand for steel products, the establishing of a steel plant was brought up again.

At this juncture a rolling mill was erected by private sector, INSIG (Iran National Steel Industries Group) to produce structural steel by rolling imported semi-finished steel products. INSIG also constructed a steel making shop (Electric Arc Furnace and continuous casting) to produce semis by melting steel scrap.

Parallel with the private sector’s activities, an inter-governmental contract was concluded between the governments of USSR and Iran to transfer the natural gas from Iran to the former USSR. In exchange for heavy industry, a steel making shop with annual capacity of 550,000 tons in Esfahan was included.

For this purpose, National Iranian Steel Corporation was established for construction of the plant and mobilization of the relevant mines such as iron ore, coking coal, limestone, refractory , etc. The plant was successfully commissioned and came into operation in 1971.
Subsequently, a contract for expansion of Esfahan Steel Plant to a capacity of 1.9 million tons/year of structural steel was signed with the previous supplier.

After a few years of operation, both the private sector furnaces and Esfahan Steel Plant were facing some problems such as shortage of scrap and quality coking coal.
These two problems on one side, and the following aspects on the other side:
-Increasing domestic demand for Iron and steel,
-Huge available resources of natural gas and required raw materials, in particular, iron ore,
-Relative Iranian expertise in iron and steel industry,
-Introduction of new methods of Direct Reduction Process in industrial and commercial scales,
contributed to establishment of another state-owned company under the title of National Iranian Steel Industries Company (NISCO) in mid-1970 to produce iron and steel products by utilizing Direct Reduction process as well as to mobilize the relevant iron ore mines.

To accomplish this, two contracts were signed between NISCO and foreign companies to construct two integrated steel mills in Bandar Abbas and Ahvaz and a heavy rolling mill in Ahvaz.

After the Islamic Revolution in 1979, fundamental changes took place in the Iranian Steel Industry Organization. The two  state-owned companies were merged and NISCO affiliated to the former Ministry of Mine and Metals and Ministry of Industry and Mine was established.

NISCO is directing and supervising the Iranian steel industry from exploration stage of its relevant raw materials up to marketing its products in domestic and international markets.

NISCO established an integrated steel mill, the Ahvaz Steel Complex, and a hot rolled plate producer, the Kavian Heavy Plate Mill, in Ahvaz , Khouzestan province in the south west of Iran. By year 1994, the 2 companies had merged to form “Khouzestan Steel Company”.
In order to satisfy the demand in hot and cold rolled coils, NISCO established an integrated steel complex, the Mobarakeh Steel Company, in Isfahan which started production in year 1992 with an annual capacity of raw steel of 2.5 million tons. Mobarakeh’s capacity stands today at close to 3.5 million tons per year and is expected to reach 4.5 million tons once all the expansion projects are in place.
Today, Iran’s steel output stands at close to 8 million tons per year, 1.2 million tons of which is produced by the private sector. This is still well below the annual consumption level of 13 to 14 million tons. That’s why the industry has seen a surge in the level of imports which stood at over 3 million tons for the first 6 months of the current year. This figure shows a 119 percent increase over the figure for the same period last year.

As a result of the shortage, many new and expansion projects are in place in order to fill the gap. Here are some of the more notable ones:

1- The Hormozgan Steel Complex near Bandar Abbas: A consortium led by SMS Demag, has signed an agreement with NISCO to build a mill to produce over 1.5 million tons of slab in addition to a lime calcining plant. Another contract for a Direct Reduction plant has been signed with the German-registered Mines & Metals Engineering.

2- The expansion phase of Esfahan Steel Co., the Saba Steel Complex, to produce over 700,000 (seven hundred thousand) tons/year of hot rolled coils: It has successfully been commissioned and is currently in its testing phase.

3- The Tin Plate Unit at Mobarakeh: This unit was inaugurated in September 2003 by president Khatami and is expected to reach its full capacity of 200,000 (two hundred thousand) tons/year in year 2004.

4- The pelletizing plant in Sirjan:
Nisco has signed an agreement with Germany’s Lurgi regarding building a 4 million tons-a-year pelletizing plant in Sirjan to be run by Gol-e Gohar Iron Ore Company.

5- The Chador Malu Pelletising Plant:
A Japanese consortium led by Kobe Steel, has signed a contract to supply Chador Malu Mining and Industrial Company equipment for a new 3.4 million tons/year iron ore pelletising plant in Ardakan, Yazd Province.

6- Tinplate Complex in Tabriz:
Danieli, the Italian steel mill manufacturer, is planning to participate in the construction of a 200,000 (two hundred thousand) tons/year tinplate mill in Tabriz.

Steel Pipe and Profile Industry
One of the biggest consumers of steel coils and plates is the pipe and profile industry. This industry currently consists of over 90 companies with a total production capacity of 1,920,000 (One million, nine hundred and twenty, thousand) tons per year.
Saveh Rolling & Profile Mills with an annual capacity of 1,200,000 (one million two hundred thousand) tons, has not only the largest market share but the most variety of pipes and profiles manufactured in Iran. It is also the largest Iranian exporter of pipes and profiles to every corner of the world.

As the largest state-owned steel company in the Middle East, NISCO ranked 26 in the table of the world’s major steel producing companies in 1999 and 2000. NISCO is also a regular member of the International Iron & Steel Institute.

During the Iraq imposed war, the steel industry development lost its impetus to some extent. However, immediately after the cease-fire and implementation of the First & Second Five-Year Economic, Social & Cultural Development Plans of the country, the steel industry achieved a considerable growth. It is worth mentioning that the steel production volume, which didn’t exceed an annual one million tons in 1988, reached 6.3 million tons in 1999 and 6.6 million tons in 2000.

Considering the country’s rich energy resources, raw materials, human resources and available technological capabilities, there is an appropriate background in investing in steel industry of the country. NISCO’s current installed capacity is 8 million tons per annum and necessary measures have been taken to increase the capacity to 10 million tons a year.

Further study is underway to expand the capacity up to 14.7 and later to 18.4 million tones per year. This company has also taken significant steps toward upgrading the quality of its products and improving the management system with due consideration to environmental protection and better working conditions.

Source: NISCO-Iran

STEEL INDUSTRY IN IRAN (History)

In 1927, plans were drawn up to establish smelting works in the north of the country to produce rail tracks domestically. This action was in connection with the go-ahead given by the parliament (Majles) to start the construction of a railway between Kòor Musa@ and Moháammara. Out of the railway budget, 4.5 million toma@ns were earmarked for this purpose, and a German expert was engaged to make a feasibility study. Suitable iron had been found near Semna@n, but no coal. The works would be dependent on the ˆemæak coalmine, which was about 100 miles away, so a special railway would have to be built between the mine and the works; moreover, it was feared that the ore deposits at Semna@n would be exhausted in fifteen years if the works were to operate at full capacity. As a result, the project fell through at the end of 1928. In early 1928 bids had actually been invited, despite the fact that the feasibility study had estimated the costs to be twice the amount which the Majles had allotted, while the German Krupp corporation, one of the world’s principal steelmakers and arms manufacturers until the end of World War II, even estimated the costs to be much higher.

Although the government shelved the project for the moment, it did not forget about it. In 1938, an agreement was reached, after much study and preparation, between Iran and a German consortium (Demag-Krupp) for the construction of two blast furnaces with a daily production of 150 tons, a steel factory, a rolling mill, a wire-drawing mill, a foundry, a wrought ironworks, a coke crusher, a power plant, and some ancillary industries such as a lime plant, an ammonia and benzol plant, and a tar distillation plant. The works were to be completed in three and a half years time and would employ 1,200 workers when working at full capacity. The original site was planned to be south of Tehran near the cement works, but Karaj was chosen instead, because of its more suitable water supply. A disadvantage, however, was that coal supplies for the power plant and the blast furnaces had to be transported from ˆemæak and Zira@b at about 35 miles distance. In 1939, Rezµa@ Shah laid the first foundation stone, and, although work proceeded as planned, the works were still unfinished in 1941 when the Allies invaded Iran. This event meant, of course, that the whole project was jeopardized, for all relations with Germany (q.v.) were cut, which led to the demise of the project. Part of the machinery was still at sea when World War II broke out and was seized by the Allies, and the rest remained in Germany and rusted away. The partly completed buildings at Karaj became dilapidated (Floor, 1984; Koellner). There were also a small number of traditional iron foundries and blast furnaces in Ma@zandara@n, and the erection of a new plant in that area to smelt 300 tons of iron per day was being considered (Gupta, p. 75; Elwell-Sutton, p. 104).

After World War II, the government wanted to complete the Karaj factory (subject to availability of coal) to manufacture rails, sleepers, iron beams and sheets (Za@hedi, pp. 58-64). However, the Overseas Consultants’ report advised against it (Roberts, p. 234; Overseas Consultants, IV, pp. 184-85). Since then, “more has been said and less done about a steel industry than any other industry in Iran” (Echo of Iran, 1965, p. 277). For the government persisted in its desire to have a steel mill and hired a continuous flow of 25 different groups of consultants, who all came to the same conclusion that the steel mill was not viable. Although the Krupp corporation agreed in 1952 to renew its contract to build the mill, the World Bank (International Bank for Reconstruction and Development, IBRD) refused to finance the project in 1959. In 1961, a proposal prepared by the London-based Kaiser Engineers Corporation for a rolling mill at Karaj, as the first phase of an integrated steel mill, also was unable to obtain IBRD financing. The project then was shelved, although funds had been allocated in the Third Development Plan. A project for a private foundry in Khuzestan to process imported scrap (35,000 tons per year) was approved. The project was only realized in 1963, when an agreement was reached between a private Iranian and a Swedish company to build the scrap metal steel mill. Meanwhile, the army’s munitions factories acquired a five-ton foundry and the Iranian State Railways a 10-ton per day electric arc foundry. Ma@æinsa@zi-ye Ira@n, a private company, built a cast-iron foundry in 1960 at Ahva@z (q.v.) with an annual capacity of 6,000 tons. It produced mainly cast-iron pipes (Echo of Iran, 1963, pp. 277, 297; 1965, p. 239).

The basis for future steel production in Iran was laid by the signing of a contract with the USSR in 1965 to finance and erect a steel plant in Isfahan (National Iranian Steel Company, NISC). Repayment of the loan was done through deliveries of natural gas from Iran to the USSR. The state-owned plant consisted of four production units using blast furnace processing technology with a production capacity of 550,000 tons per year. The Isfahan steel plant (Aryamehr Steel Mill, later called Dòawb-a@han-e Esáfaha@n) was commissioned, and its cast iron department came into operation in 1971. At that time, a contract for the expansion of the Isfahan steel plant to a capacity of 1.9 million tons per year of structural steel was signed with the USSR. Work started in 1973, but due to political and economic upheaval the plant was not completed until 1983. The private-sector Iran National Steel Industries Group (INSIG, Goruh-e Melli-ye S®an¿ati-ye Fula@d-e Ira@n) erected a second 85,000 tons per year rolling mill (ˆa@hin), also at Ahva@z, in 1969, and ordered a third one (ˆahya@r, 120,000 tons per year) to produce structural steel by rolling imported, semi-finished steel products. Later the two plants were referred to as Navard Iran. INSIG also constructed a steelmaking shop (using an electric arc furnace [EAF] and continuous casting [CC] technology) to produce semis by melting steel scrap. Two other bloom plants for processing sponge iron (400,000 tons capacity) were erected in 1972 by the ˆahriya@r Industrial Group; they were nationalized after the Islamic revolution and are now managed by the National Iranian Steel Industries Company (NISCO). The Ahva@z complex supplies these two plants. Also built were the Ahva@z Rolling and Pipe Mills Company to produce 140,000 tons of skelp (steel shaped for pipe-making) per year and the ˆahriya@r Pipe Manufacturing Company to produce 80,000 tons per year of seamless and galvanized pipes (0.5-5 inches diameter), both in 1973.

The problems encountered at the Isfahan steel plant and the private sector furnaces (shortage of scrap and quality coking coal) constrained the government’s policy to expand the country’s iron and steel industry to respond to growing domestic demand. The development of new methods of direct reduction processing technology provided a viable alternative for the government, given the fact that Iran had rich resources of natural gas and various required raw materials, in particular, iron ore. The resulted in the establishment of another state-owned company under the name of NISCO in the mid-1970s to produce iron and steel products by utilizing the direct reduction process, as well as to mobilize the relevant iron ore mines. To accomplish this, two contracts were signed between NISCO and a European-American consortium to construct two integrated steel mills in Bandar-e ¿Abba@s (q.v.) and Ahva@z and a heavy rolling mill in Ahva@z.

After the Islamic Revolution in 1979, fundamental changes took place in the Iranian Steel Industry Organization. The two state-owned companies were merged, and NISCO was affiliated to the former Ministry of Mines and Metals, and the Ministry of Industries and Mines was established. NISCO now directs and supervises the Iranian steel industry from the exploration stage of its relevant raw materials up to the marketing of its products in domestic and international markets. As the largest state-owned steel company in the Middle East, NISCO ranked 26 in the table of the world’s major steel producing companies in 1999 and 2000. NISCO is also a regular member of the International Iron & Steel Institute.

During the Iran-Iraq war (1980-88) the steel industry development lost its impetus to some extent. Construction of the Ahva@z Steel Complex (Mojtame¿-e Fula@d-e Ahva@z) had been started in 1974 with a planned capacity of 2.35 million tons per year. Completion was scheduled for 1983, but was delayed by damage due to Iraqi air raids, and the plant cost 40 percent more than originally estimated. However, immediately after the cease-fire and implementation of the First and Second Five-Year Development Plans of the country, the steel industry achieved a considerable growth. In 1988, the volume of steel production did not exceed an annual one million tons. However, it reached 6.3 million tons in 1999 and 6.6 million tons in 2000. This was due to the completion of old projects and the implementation of new ones. Of the old projects the most notable was the Ahva@z Steel Complex, which is built 12 km from Ahva@z on a terrain of 300 ha. The first of the plants was ready for operation in 1989 with a capacity of 550,00 tons per year. Its 150 x 150 mm steel ingots are supplied to NISC, which transforms them into beams and round bars.

The second and third phases (two furnaces and a casting unit) of the Ahva@z Steel Complex were completed by 1989 and 1990, respectively, with a production capacity of 1.6 million tons per year; this output is converted into sheets by the Ka@via@n heavy rolling project (Na@vard-e Sangin-e Ka@viya@n), which is part of the Ahva@z steel complex. Work had started on the Ka@via@n plant in 1976, and it was completed (with delays) in 1989. Its output consists of 400,000 8-40 mm sheets and 300,000 tons of slabs, while it also converts slabs into billets and blooms using the hot rolling method. At Ahva@z there is also the Nasr Steel Mill (Fula@d-e Nasár), which produced 125,000 tons of steel billets in 1988. Its design capacity is 360,000 tons. The Khuzestan Steel Production Complex produced 1,698,000 tons of steel in 2002-03, hitting a record in its annual production. The complex was to produce almost two million tons of steel in 2003-04. Khuzestan Steel Co. (KSC) actually consists of three companies (Ahva@z Steel Complex, INSIG, and Ka@via@n), but in early 1994 NISCO, the mother company, decided to integrate them into one company to better compete in the world market. Further upgrades and expansion also took place at the Isfahan Steel Mill in 1989 when the Italians completed two continuous casting units.

One of the first new projects was the construction of the Iran Alloy Steel Plant (Fula@dha@-ye Alya@ji-ye Ira@n) at Yazd, which started in 1988 and became operational in 1998. It has a production capacity of 120,000 tons of alloy steel sections and 20,000 tons of alloy steel ingots. The capacity may be raised to 200,000 tons later.

Another new project was the Mobarakeh Steel Complex (Mojtame¿-e Fula@d-e Moba@raka), which is the biggest industrial project in Iran. It has been built by an Italian consortium and is located on 35 sq. km of land and has 28 associated plants as well as a number of non-associated ones. Originally it was planned to be built at Bandar-e ¿Abba@s, but it was decided to build 75 km to the southwest of Isfahan to be closer to the Ùa@dormalu coal mines, which added much to the cost of its final products. The Mobarakeh Steel Company is affiliated to NISCO and is also the first integrated flat steel production plant in the Islamic Republic of Iran based on DRI [“direct reduced iron” oxidation]-EAF-CC technology. The plant became operational in late 1992 with a projected production capacity of 2,935 million tons of liquid steel per year. The current capacity is estimated at 2.8 million tons per year. Expansion of the plant to an annual capacity of 4.1 million tons is under way. The expansion contract was signed between Iran and three Italian companies on a buy-back basis.

INSIG (as noted above, part of KSC) also initiated the construction of new capacity such as a bar rolling mill financed by the Italian steel corporation Danieli with a capacity of 550,000 tons of bars on a yearly basis. It also intends to reconstruct its casting and melting shops to increase production to 470,000 tons of crude steel when financing has been secured. INSIG is situated on the Ahva@z-Kòorramæahr road and was nationalized after the revolution. It has seven plants in five sections, including three rolling mills, the first of which started operating in 1967. The INSIG group produces knurled and plain bars, drawn wires, iron beams, angle irons and belt in section 2. Steel and steel girders are made in section 3, while section 4 has two galvanized and non-galvanized pipe-making units (70,000 and 120,000 tons capacity, respectively). The necessary machines are assembled in section 5.

The Isfahan Steel plant will add new capacity to produce some 3.6 million tons of crude steel. The Saba Steel Complex, near Isfahan, which has been designed and constructed by Isfahan Steel Mill, adds a total of 700,000 tons of steel sheets to the country’s annual production. The Khorasan Steel Complex in Nishapur (51 percent privately owned, 49 percent Isfahan Steel) with an annual capacity is 550,000 tons became operational in 2002. Its capacity will be increased with a sponge iron plant and capacity will be increased to 1.3 million tons. The Meybod Steel Project has a capacity of 300,000 of cast iron per year. The Zagros Steel Project in Kurdistan province has a capacity of 70,000 tons of cast iron per year. It is planned to add an agglomeration plant later. The Hormozegan Steel Project has a planned capacity of 1.5 million tons of crude steel. Hormozgan Steel Complex signed two contracts in January 2003. A contract worth USD 300-400 million, for the construction of a 1.5 million-tons-per-year slab and lime calcining plant, was signed with a consortium of Germany’s SMS Demag AG, Iran International Engineering Company (IRITEC) and its subsidiary registered in Italy, Irasco. The estimated USD 140 million contract for the setting up of a 1.65-million-tons-per-year direct reduction iron facility was signed by Germany-registered Mines & Metals Engineering GmbH (MME). NISCO will be the operator of the plant. Financing will be arranged on a buy-back basis, with a structure similar to the one used for the expansion of the Mobarakeh Steel Complex. The buy-back agreement will cover both the project’s international and local content.

To sustain the expansion plans of the steel industry (in particular at Isfahan Steel and Mobarakeh Steel), the ongoing Bandar-e Abba@s Jetty project will enable the handling of 5 million tons per year of minerals at the port, allowing the docking of ships with a capacity up to 150,000 tons. Likewise the Bandar Imam Jetty project enables the handling of 5 million tons per year of iron ore at the Khuzestan Steel Complex. Ships with a capacity of 60,000 tons can dock of the jetty, while further dredging will allow docking of ships of 100,000 tons. Not only port access and capacity are important for Iran’s steel industry, but also the railway system. According to the Ministry of Industries and Mines, 50 per cent of total railway capacity was allocated to transporting the output of the National Steel Company in 2000, and with planned increase of steel production capacity more demand will be made on rail capacity.

World steel production in 2000 reached 850 million tons, of which Iran’s share was 6.7 million tons; Iran then ranked twenty-third among steel-producing countries, and twenty-first in 2004. NISCO reported that the annual production of steel in Iran for 1382 (2003/04) was estimated at 8.13 million tons—the first time that Iran’s steel production would surpass eight million tons. This meant that Iran was able to satisfy 70 percent of domestic demand, while at the same time exporting some 1.5 million tons of steel. Exports constitute a small part of the output of the steel and other metal industries. Only ingots and some aluminum was exported and amounted to less than 1 percent of total exports in 1999. As to imports, except for universals, plates, and sheets (UN International Trade Centre, no. 674), tubes, pipes and fittings (678), and bars, rods, shapes, sections (673) all imports were less than 1 percent of total imports. The location of the Mobarakeh plant at Isfahan rather than near Bandar-e ¿Abba@s constrains its export capacity due to high transportation cost. Investments are ongoing to expand the capacity up to 14.7 and later to 18.4 million tons per year. NISCO has also taken steps toward upgrading the quality of its products and improving the management system with due consideration to environmental protection and better working conditions.

Iran was scheduled to produce some 8.1 million tons of steel and 7.6 million tons of steel slabs in 2003. In 2002, about 7.5 million tons of steel, as well as 7.5 tons of steel slabs were produced in the country, so the country is capable of producing steel and steel slabs in equal amounts. However, the domestic consumption of steel was as high as 11 million tons in 2002, which meant that more than 3.5 million tons of steel were imported. The domestic consumption of steel for 2003 was predicted to be some 12 million tons, which is likely to increase with a boom in the construction sector. This is because, unlike many countries in the world which use concrete and bars, Iran uses iron slates in construction, which also adds to the instability of its buildings. Despite all, Iran managed to export 1.5 million tons of steel products in 2002. Iran’s steel is capable of competing with European products due to its quality and price. The only issue obstructing its path to more exports is domestic demand that outweighs production.

The prospects of Iran’s steel industry seem favorable due to its large and rich raw material resource base, its rich and cheap energy resources, human capital and technical know-how. Iran not only added new capacity during the last 20 years that significantly reduced the country’s import bill and even made export of steel products possible, but it also developed its own technological capacity. Iran, for example, developed its own direct reactivation method of producing iron with 96 percent “metallization,” which works more effectively than the three other conventional methods. The method has been patented and licensed to an Italian company. The Isfahan Steel complex also has been developing innovative techniques of producing spongy iron, manufacturing macro-weighty crafts, etc. Takado Company was established as an investment company and was an affiliate of Isfahan Steel. It started operating with personnel from Isfahan Steel, and after a decade it became one of the largest investment companies in the steel industry. It consists now of 13 companies and has 25 affiliated companies, and it is involved in most aspect of the steel industry.

Direct Reduction Process (MIDREX)

The Midrex ™ Direct Reduction process is based upon a low pressure, moving bed shaft furnace where the reducing gas moves counter-current to the lump iron oxide ore or iron oxide pellet solids in the bed. The reducing gas (from 10-20% CO and 80-90% H2) isproduced fromnatural gasusing Midrex’s CO2 reforming process and their proprietary catalyst (instead of steam reforming).
A single reformer is utilized instead of a reformer/heater combination. The reformed gas does not need to be cooled before introduction to the process. There is also no need for a separate CO2 removal system. The process can produce cold or hot DRI as well as HBI for subsequent use as a scrap substitute feed to a steelmaking melting furnace (SAF, EAF or oxygen steelmaking process). Over 50 Midrex™ Modules have been built worldwide since 1969. They have supplied over 60% of the worlds DRI since 1989.

midrex
PROCESS DESCRIPTION:
The iron oxide feed to a Midrex shaft furnace can be in the form of pellets, lump ore or a mixture of the two (in 0 to 100% proportions). The solid feed is discharged into a feed hopper on top of a proportioning hopper that evenly distributes the solids into the shaft furnace.

A dynamic seal leg keeps the reducing gas inside the furnace. The shaft furnace operates at low pressure, under 1 bar gauge, which allows dynamic seals to be used on the furnace inlet and discharge. The iron ore burden in the shaft furnace is first heated, then reduced by the upward flowing, counter-current reducing gas that is injected through tuyeres located in a bustle distributor at the bottom of the cylindrical section of the shaft. The ore is reduced to a metallization typically in the range of 93% to 94% by the time it reaches the bustle area.

Below the bustle area, it goes through a transition zone (with design to reduce agglomeration or lumping) and then reaches the lower conical section of the furnace. Lower carbon reduced iron (<1.5% C) is cooled using a circulating stream of cooled exhaust gas that is introduced in the conical section for cold DRI discharge. Higher carbon DRI (up to 4.0% C) can be produced by introduction of natural gas into this cooling gas. It readily reacts (and cracks) with the highly reactive metallic DRI.

For hot discharge of DRI to be used for hot charging of EAF’s (i.e. Midrex’s Hotlink™ Process) or for feed to hot briquetting presses (to produce HBI), the lower part of the furnace is modified to allow handling of hot burden.
The Midrex gas generation system consists of a CO2 reformer using their own catalyst. The feed to the reformer is a mixture of process gas recycled from the furnace and makeup natural gas. The top gas leaving the shaft furnace at a temperature of 400 to 450C is cooled and dust is removed in a top gas scrubber. About two-thirds of the gas is recycled back to the process (process gas) and the rest is used as a fuel. The process gas is compressed, mixed with natural gas and is preheated in the reformer recuperator before entering the tubes of the reformer.

The reformed gas comprising of mostly CO and H2 exits the reformer at about 850 °C and passes through collection headers to the reformed gas line. The ratio of H2 to CO is controlled at about 1.5 to 1.8, and reducing quality at 11 to 12 for best operation.